So the 2nd runway does have it’s uses after all!
Basic thrust of that page:
23R/05L to be resurfaced, rewired and get better lighting starting in January and it won’t be completed till September – it’s scheduled to take place at nighttime 5 times a week (times it is closing: 2130-0600 Sundays to Thursdays). Cost is £20 million.