dark light

Abhimanyu

Forum Replies Created

Viewing 15 posts - 736 through 750 (of 832 total)
  • Author
    Posts
  • in reply to: Indian MMRCA saga – Jan 08 #2480389
    Abhimanyu
    Participant

    And clearly according to you the development of a something such sophisticated as an aircraft starts even before the project definition is complete.Obviously thats how things are done in your country…why am I not surprised…

    rayrubik, actually Buraidiah’s quotations of Dr. Harinarayana were accurate. However, he misinterpreted the first metal cutting in 1993 to be a delay due to ADA, and not IAF.

    I once again reproduce the excerpt from the article I posted earlier :

    After consideration, including by special committees, the Indian Air Force and the government gave the real operational go-ahead only in late-1993.

    Buraidiah later validly questioned about the beginning of not metal cutting, but the design, to which it was replied that PD began in sept. 1987 till 1988 after which 1/7 scale model was tested in 1990.

    In the 1970’s (not 1978 in particular), only the need for such a fighter was informally or unofficially put forward, just like the need for MRCA was first proposed sometime in 2001. The agency to develop the Tejas itself was formed in 1983.

    in reply to: Indian MMRCA saga – Jan 08 #2480531
    Abhimanyu
    Participant

    We are discussing about project start date here not when the iron was cut or composite tech imported date:dev2: If you really want to know when LCA was planned and the requirement elucidated from user you can take that as 1978, Yes 1978 the date when LCA studies began.

    I disagree with the above. In 1978, only a need for such a fighter was unofficially concieved. From 1983 to 1990, the PD was prepared, personnel were hired and necessary facilities of construction were setup.

    Other than metal cutting in 1993, if the time line of design is to be considered, then it can be said to be around 1989, when the 1/7 scale model of the Tejas was developed and then tested in 1990. This was based on PD which began to be formulated in Sept. 1987 and completed in 1989.

    If LCA is pioneering effort to you so be it, but it was not the case for SAAB, BAE, or Dassualt. For, they were building one aircraft after another regularly and each one of them is as much poineering as the succeding one.

    All the planes mentioned above were significant departures from the earlier projects; in case of India the transition was from post WW2 HF-24 Marut, to a 4+ G fighter like Tejas. Same was the case of Japanese F-2 after WW-2 planes, and the USA’s F-22 from F-15. In case of Typhoon, it was a first effort totally.

    in reply to: Indian MMRCA saga – Jan 08 #2480611
    Abhimanyu
    Participant

    Glad you came down from 1993 BS, so lets bring it further till you arrive at 1983:p. According to you a project start where cutting the plate for plane???

    LCA was originally conceived in 1978but it was only sanctioned ahd entrusted to the Aeronautical Development Agency (ADA) in August 1983 for completion in eight to ten years. ,
    http://www.flightglobal.com/PDFArchive/View/1988/1988%20-%203419.html

    As you can see the LCA was conceived in 1978, and Govt sanctioned it only in 1983.

    So, do you think the developers fooling the Govt and the people??? Are they comiiting to something which they knew they could not fulfill?? That will make them……:D

    Note that as per Air Marshall Wollen (retd) and the article by Mr. Raman Puri and Ashok Parthasarthy, the production of Tejas began in 1993 only, due to the inordinate delay by the IAF. The IAF along with numerous govt. committees, delayed the final clearance to late-1993 instead of 1990, prior to which production could not begin.

    Thus, from the above it is clear that Tejas got delayed by procedural delays by IAF and govt. committees, and not due to ADA.

    Hence, as the Tejas actually began production in late-1993, the development time of the Tejas has been 15 years only and not 23 years as the media claims. Even if one does “latch on” to the date of 1983, it can be noted that most of the time from that year upto 1993 was spent in sanctioning, preparing PD, reviews, and giving operational clearance and other such bureucratic delays only.

    This discussion of LCA and its never ending story is coz someone posted LCA is in league of F-22, Typhoon, Rafale ……..and hence can also be in running of MMRCA.

    We have discussed before that the context of that discussion was the pioneering effort of the countries of the aircraft mentioned.

    The onus may now be on you to prove how Tejas cannot compare to Gripen, Rafale and Typhoon in the technologies involved like avionics, radar, weaponry, and stealthiness as we have already discussed in opposition to this issue before.

    in reply to: Indian MMRCA saga – Jan 08 #2480759
    Abhimanyu
    Participant

    I think now we have established that the build up of infrastructure and feasibility studies started in 1983 or afterwards…and this does make sense since India needed time to build a basic aviation industry prior to taking up the full scale development of LCA. Now the next question is while all this was going on, i.e. feasibility studies etc, when did India start any actual design work on LCA?

    Actually this thread is “inundated” by the responses and counter-replies by scorpion82 and star49, because of which a coherent discussion may be difficult to track.

    vikasrehman, I am reproducing an article I posted on page 3 of this thread (post # 90) :-

    The two issues on which the LCA project is criticised are cost and time overruns, and performance shortfalls. As regards the so-called time overruns, when the zero/go date for the project is taken as 1983, the critics fail to mention that what was sanctioned in 1983 was an ad hoc Rs.560 crore, pending full preparation of the Project Definition Document (PDD) — which is a fundamental step even to start the design and development process. The costs were to be finalised based on the PDD. This required the setting up of infrastructure in a hundred academic institutions and R&D laboratories and building up expertise to undertake the fundamental and application-oriented R&D required, and harnessing the design and engineering effort available largely in the public sector units for such a complex, state-of-the-art aircraft. The Aeronautical Development Agency (ADA) discussed with Air Headquarters the Air Staff Requirement (ASR). Air Headquarters had requirements added to what was originally to be a replacement for the MiG-21. As a result, the ASR that was finalised was practically that for a Mirage 2000. But in the public perception the LCA remained as a replacement for MiG 21.

    It look seven years, till 1990, to formulate the PDD. Based on this the ADA, in a report to the Ministry of Defence in 1990, gave a time-frame of seven years to develop the LCA and projected a financial requirement of Rs.4,000 crore. This included the building of four prototypes also. There had been a 25-year gap since the only fighter aircraft ever indigenously designed, developed and manufactured, namely the HF-24 Marut, had entered squadron service. So the period of seven years to set up a more advanced R&D infrastructure and build up even the core personnel needed to develop the technologies that the LCA’s ASR and PDD called for, was modest.

    After consideration, including by special committees, the Indian Air Force and the government gave the real operational go-ahead only in late-1993. Even that “go-ahead” covered the development of only two Technology Demonstrator Aircraft (TDA) without weaponisation. The funding approved was only of Rs.2,000 crore — half the amount requested for full-scale development. The first TDA flew in 2001, eight years from the real operational ‘go’ date, despite much additional R&D work that had to be undertaken due to the U.S. sanctions imposed in 1998.

    To the above, I may add from Air Marshall Wollen’s article, that from 1987 to 1989 the Project Definition (PD) document was prepared with consultancy from Dassualt aviation. This paper provided the design of the Tejas and its accompanying technologies. A Review Committee was formed in 1989 which cleared the Tejas project. The work was to begin in 1990, but began in April 1993 only due to an IAF delay in finalization.

    However, in 1989 the construction of a 1/7 scale model of the Tejas was begun and completed in 1990. The same was tested in the wind tunnels of a French aviation company. This model was finalized into the full-scale model.

    Please also note that the author of the article from Bharat-Rakshak monitor is not a forum member, but Air Marshal MSD Wollen (Retd), who served as the chairman of Hindustan Aeronautics Limited from September 1984 to March 1988. His views are not only accurate, but also authoritative and finally binding.

    References :-

    The case to support the indigenous LCA programme, Ashok Parthasarathi and Raman Puri

    The Light Combat Aircraft Story, Air Marshal MSD Wollen (Retd)

    in reply to: Indian MMRCA saga – Jan 08 #2482079
    Abhimanyu
    Participant

    The Light Combat Aircraft (LCA) project was launched in 1983 and hopes for a first prototype flight by 1992. The aim is to produce a state-of-the-art single-engined,multirole, all-weather fighter. Following the critical-review stage, a compound-delta planform was chosen for the wing. ADA freely admits that many of Dassault’s software tools were used in the design process, together with access to the French company’s knowledge base. Involvement by the USA has been limited to flight control systems, composites and avionics simulation, for key systems such as the radar, the ADA is carrying out a joint definition effort with Ericsson of Sweden.

    The above is inaccurate. While Dassualt’s consultancy was taken in the Project Definition (PD) stage, composites and avionics simulation were not done by USA. In Project Definition stage, an on-paper plan or “sketch” of the plane is created. Some CAD-type tools may have been used at that time to arrive at the PD on paper.

    Note that Tejas is said to be globally the first fighter of all time to have a compound cranked delta planform.

    Selling software and manufacturing composite is two different things…….. here is what reality is:
    Carbonfibre technology for the wing will also be imported, as NAL would take nine years to begin production of composite wings, says Dr S. R.Valluri.

    The above is the same news as initial import of composite wing panels from Italy. Currently, the fabrication of all the composite structures for wings, fuselage, rudder, fin is now undertaken by NAL as mentioned in page 3 of this document. For the LSPs, NAL has already completed the setup of composite fabrication technology.

    in reply to: Indian MMRCA saga – Jan 08 #2482890
    Abhimanyu
    Participant

    How can you discuss the validity of LCA as MRCA contender when, LCA is compared with F-22, and F-16 is branded as third generation. Do you expect us to take the article seriously.

    See, we have discussed before that the author was discussing pioneering efforts for their respective nations. F-2, Ching-Kuo, F-22 and Tejas have all this aspect in common. F-22 was the first 5th G project of the US and Typhoon was also the most sophisticated project undertaken by the EU.

    It is not the news report or opinion of the journalist but former IAF Chief, Hope you won’t discredit him.

    See, there is no harsh question of “discrediting” etc., but ADA’s information can also be put forth with equal conviction. The import content and indigenous content have been detailed by various DRDO affiliated websites, that are available in the public domain.

    You can refer to page 13 of this document, to see a list of most components of the Tejas and manufacturers.

    Air Chief Marshal S K Sareen said that the indigenous components in the LCA were few. ‘‘Only 30 per cent of the airframe is Indian, the fly-by-wire control, avionics and engine are not ours,’’ he said. ‘‘So who are we fooling by saying that 70 per cent of the LCA is indigenous,’’ he asks,

    I’m afraid, with all due respect to Air Marshal Sareen, the above is inaccurate. Only the testing and integration was done using F-16 Vista sims and other equipment from Lockheed, as India lacked the necessary equipment for the same, just as Kaveri was tested using a Russian high altitude bomber, or the ejector seat was tested and certified by Martin Baker, or the first 1/7 scale model was tested at a French firm’s facility.

    After Indian scientists were asked to leave the US following the Pokhran-2 tests, the remaining testing and integration of the FBW was done indigenously under Dr. Kalam.

    in reply to: Indian MMRCA saga – Jan 08 #2483580
    Abhimanyu
    Participant

    Buraidiah, the focus of discussion is Tejas’ viability as an MRCA contender. The information posted by you regarding Dassault and costs incurred in every phase has already been in the public domain since 8 years as in here.

    Please understand that the test rigs, simulators and integration for FBW was done using F-16 Vista sims, as is mentioned on various articles on Tejas, including wikipedia.

    Here, I would briefly digress from the topic to focus on the oft-quoted media phrase of, “wings from Italy and avionics from France”. Only the frontal display panels are sourced from France : processors and mission computers that run in the background are Indian developed, as in Su-30 MKI.
    ADA has beaten major composite manufacturers in the sale of software to Airbus Industrie, which is used for designing 3-D composite layout. This does not imply that the latest Airbus A-380 is Indian, instead of French. Similarly, if initially Italian composites were purchased, it doesn’t imply that the Tejas is Italian.

    Mr. Hormuz’s article “clubs” Tejas, Gripen, F-22, Typhoon and F-2 because they were pioneering efforts for their respective nations.

    in reply to: Indian MMRCA saga – Jan 08 #2483705
    Abhimanyu
    Participant

    star49, I think you are emphasizing on range-payload requirements only, to measure the fighter generation, whereas it is measured in the complexity of technologies involved.
    As an example, the lightweight Gripen, and F-18 super Hornett have widely differing max. payload and ranges. The difference in max. payload of MiG-35 and Rafale is 3,000 kgs.
    Yet, all these planes are in 4+ category because of employing some or all technologies like TVC, AESA radar, unstable airframe controlled by digital flight-control, highly integrated networking, high tensile composites etc. Except TVC, Tejas already does, or will fully employ all the remaining technologies.**

    The IAF’s MRCA contract is often said to emphasize more on such technologies than only range-payload. This may explain why the “full spectrum” of fighters from lightweight Gripen to heavier twin-engined F-18 and MiG-35 were all sent RFPs.

    However, the “mindset” generated by the Indian media is that Tejas has no other purpose than a “lightweight”, “low tech” and “low cost” replacement for MiG-21 only. But as per the recent article by Mr. Hormuz, the Tejas has a payload equal to the twin-engined MiG-29 fighters, and has all technologies of 4+ G fighters including sensor fusion. As most fighters under ANY mission profile, do not carry more than the stipulated 3,000 kgs of external weapons, the Tejas can also meet the MRCA requirement, because such a weapon load is well within its max. capacity of >4,000 kgs. The authors of the highlighted article I posted earlier mention that Tejas is equivalent or superior to upgraded Mirage-2000 in 4+ G technologies, and hence the Tejas can be a viable MRCA contender, if the govt. so allows.

    References :

    Article about Tejas by Mr. Hormuz Mama

    ** As per recent news reports, EADS has offered an AESA radar for Tejas. Also, a further milestone for Kaveri is addition of TVC.

    in reply to: Indian MMRCA saga – Jan 08 #2484026
    Abhimanyu
    Participant

    Composites does not alone make 4+ generation aircraft. it has to be multirole. It has to lift heavy weights as M2K-9. U havent shown me photo of Teja ETs. how big they are? smallish like

    star49, Tejas is a multirole plane as per the developing Agency, ADA. It can carry air-to-air missile (recently test-fired R-73) and drop tanks. A2G weaponry will also be tested.

    Regarding its being 4+, it is because of its technologies like avionics package, digital quad FBW, Elta (and later AESA) radar, which are equivalent to Rafale or Gripen. Its composite percentage is higher than Typhoon too, as per official webpages of the 2 fighters.

    There is difference Rafale was mostly developed with indigenously developed technolgies. LCA started with imported stuff & will go indigenous over time.
    so Rafale still didnot took that much time despite budget was mostly in 1988-1992 period.

    I may reiterate that components imported for Tejas are engine (same as Gripen and T-50), cockpit displays (same as Rafale), gyroscopes, testing equipment and integration of FBW from Lockheed Martin, and the Litening pod from Israel (later version used in JSF).

    Of these, the displays, gyroscopes and target pod have been developed indigenously and are to be deployed on later production versions. The Kaveri engine development is ongoing.

    in reply to: the PAK-FA saga, continued2…… #2484109
    Abhimanyu
    Participant

    Russia offers India aviation secrets in fighter contract bid

    MOSCOW (AFP) — Russia is ready to hand India military aircraft engineering secrets in a bid to win a 12-billion dollar (7.65-billion euro) aviation contract tender, Interfax agency reported Friday.

    “If the Indian government decides to buy the MiG-35 (fighter), we will transfer to India the key technologies used in these aircraft including fifth generation technologies,” manufacturers MiG said in a statement.

    These ‘fifth generation’ elements include what analysts have said is greatly improved manoeuvrability on older models, plus a new radar system capable of simultaneously tracking, and attacking, over 20 targets from the cockpit.

    From the above news report it may be unclear that if the Russian side proposes to transfer “key fifth generation” technologies in return for winning the MRCA contract, then what technologies will be transfered/shared in the PAK-FA. Apparently, none may be shared in case of the PAK-FA, if they are being proposed for the MiG-35 itself.
    Although MiG and Sukhoi are currently separate companies, they are in the process of being integrated into one ‘conglomerate’ along with other defence firms like Sukhoi and Irkut, with Russian govt. being the majority stakeholder.

    Reference :
    http://afp.google.com/article/ALeqM5heMSADLICGIpYyGMDwHoUkAh4fog

    in reply to: Indian MMRCA saga – Jan 08 #2484275
    Abhimanyu
    Participant

    MRCA= Multirole combat aircraft
    MMRCA= Medium Multirole combat aircraft
    F-16E/EF/Rafale/MIG-35 comes around 24 tons Maximum. Only F-18/Gripen will be outliers.

    But those contenders are now claiming 4++. So u need one another Plus for LCA. I want to see the load out pictures even conceptual drawings will be appreciated.

    See, there are no 2 or more contracts, but only 1 contract for 126 fighters for which 6 contenders are said to be competing.

    The Tejas is a 4+ G fighter plane on virtue of highest percentage of co-cured composites globally, and avionics and flight-control being comparable to Gripen-C and Rafale. AESA radar is also being discussed for the same.

    No doubt it was effort under taken first time but there was foreign consultancy available in late 80s to 90s along with licensing of foreign aircraft. so it is not that India was starting from clean sheet in complete isolation from outside world. I doubt that was the case with Rafale. Rafale was technology beyond Mirage-2000 in stand alone basis.

    The Tejas project was not undertaken on a turnkey outsourcing procedure like Taiwan’s Ching Kuo, Japan’s F-2 and S. Korea’s T-50 fighters. These are F-16 clones with substantial and major contracts outsourced to Lockheed Martin and many other US companies.

    The Tejas project was commenced wholly indigenously. Where unavailable, technology was procured for example, gyroscopes and displays from France, ground rigs and simulators for flight-control from US (F-16 vista sim was used), and the Litening target pod from Israel. However, parallel development of all these is completed or ongoing.

    If, as you say, Rafale was “technology beyond Mirage-2000”, then by the same measure it may be said that Tejas may be in “another dimension” compared to post-WW2 HF-24 Marut.

    A long long time ago and in a galaxy far far away, I had written this:
    Clicky

    Victor, the above views are accurate. As you mentioned, the actual timeline for Tejas begins in 1990, and not 1983 as most critics mention.

    in reply to: Indian MMRCA saga – Jan 08 #2487495
    Abhimanyu
    Participant

    whats difference between MRCA & MMRCA. 4+ or 4++ like MIG-35?

    star49, please note that there is no ambiguity between MRCA and the so-termed MMRCA (a term which also briefly appeared in the media for some time).
    There is one and only one contract for 126 fighter planes for which there are 6 foreign contenders.

    The authors rightly say that the Tejas being a 4+ gen. fighter plane, it too is comparable to the 6 contenders, and that there is no need to import highly expensive planes.

    M-88 related to Mirage-2000.

    I agree the authors made a factual mistake there, but the point is that the M-88 too took over 15 years and $1.68 billion to develop.

    The corresponding figures for Kaveri are 17 years and < $1 billion for a nation that has NEVER attempted making a turbofan engine in its history.

    Hence in this case, the authors are accurate.

    15 year the maximum for Rafale but than there is Naval version with canards.

    Please note that the authors mention that prior to Tejas, the last aircraft developed was the HF-24 Marut over a quarter century earlier.

    Hence, the development of Tejas was a “quantum leap” , in sharp comparison to the experience of continuous, unceasing fighter development throughout many decades in France. So, the authors are accurate that the Tejas was an effort undertaken for the first time.

    Despite that, the Tejas has remained within the sanctioned amount of just $1.2 billion as compared to $6 billion for the Rafale effort. Also, the timespan for Tejas i.e. 20 years is not much more than 18 years for Rafale.

    in reply to: Indian MMRCA saga – Jan 08 #2487694
    Abhimanyu
    Participant

    The following article by Mr. Parthasarathy, former scientific advisor to the Prime Minister, and Vice Admiral (retd) Raman Puri not only describe the case for the continuation, but also the enhancement of the Tejas and most importantly, its case as an MRCA contender.

    The authors were the apex authorities on defence procurement of the 3 services upto 2006. This article is very important in that regard :

    The case to support the indigenous LCA programme

    Ashok Parthasarathi and Raman Puri

    The facts with regard to perceived cost and time overruns and performance shortfalls in perspective

    There have been several articles in the press critical of projects of the Defence Research and Development Organisation (DRDO) in general, and specifically the programme relating to the Light Combat Aircraft (LCA), now named Tejas, and the Integrated Guided Missile Development Programme. Indeed, whenever a significant event that involves indigenous R&D, particularly defence-related, occurs, or a crucial decision is set to be taken, articles originating from within the defence “system,” or from vendors who see their business prospects threatened, appear. The real facts relating to the programme need to be put in context.

    The two issues on which the LCA project is criticised are cost and time overruns, and performance shortfalls. As regards the so-called time overruns, when the zero/go date for the project is taken as 1983, the critics fail to mention that what was sanctioned in 1983 was an ad hoc Rs.560 crore, pending full preparation of the Project Definition Document (PDD) — which is a fundamental step even to start the design and development process. The costs were to be finalised based on the PDD. This required the setting up of infrastructure in a hundred academic institutions and R&D laboratories and building up expertise to undertake the fundamental and application-oriented R&D required, and harnessing the design and engineering effort available largely in the public sector units for such a complex, state-of-the-art aircraft. The Aeronautical Development Agency (ADA) discussed with Air Headquarters the Air Staff Requirement (ASR). Air Headquarters had requirements added to what was originally to be a replacement for the MiG-21. As a result, the ASR that was finalised was practically that for a Mirage 2000. But in the public perception the LCA remained as a replacement for MiG 21.

    It look seven years, till 1990, to formulate the PDD. Based on this the ADA, in a report to the Ministry of Defence in 1990, gave a time-frame of seven years to develop the LCA and projected a financial requirement of Rs.4,000 crore. This included the building of four prototypes also. There had been a 25-year gap since the only fighter aircraft ever indigenously designed, developed and manufactured, namely the HF-24 Marut, had entered squadron service. So the period of seven years to set up a more advanced R&D infrastructure and build up even the core personnel needed to develop the technologies that the LCA’s ASR and PDD called for, was modest.

    After consideration, including by special committees, the Indian Air Force and the government gave the real operational go-ahead only in late-1993. Even that “go-ahead” covered the development of only two Technology Demonstrator Aircraft (TDA) without weaponisation. The funding approved was only of Rs.2,000 crore — half the amount requested for full-scale development. The first TDA flew in 2001, eight years from the real operational ‘go’ date, despite much additional R&D work that had to be undertaken due to the U.S. sanctions imposed in 1998.

    Comments appeared in the media in 2001 quoting IAF sources to the effect that what the ADA had achieved was just a flying machine that was yet to be weaponised. Considering the nature and scope of the approval accorded in 1993, what else was to be expected? Using the money sanctioned for two TDAs, the ADA built four. Full-scale development, for which another Rs.2,000-plus crore was finally sanctioned, thus started only in late-2001. Some 1,200 hours of flight testing was to be undertaken to secure Initial Operational Clearance (IOC) from the IAF.

    At that point, apart from the weaponisation requirements the project had to undergo extensive redesign to accommodate an air-to-air missile chosen by the IAF, which was considerably heavier and longer than what had been specified till 2000. The IAF had again changed its mind. This necessitated the complete redesign of the wing structure, using only composite materials in order to keep the weight within limits. The period of this redesign was also utilised to upgrade the avionics, to a completely open architecture.

    Consequently, in “generational terms” the LCA is a fourth generation-plus aircraft with full networking capabilities. This made it more than comparable to anything the IAF had, and possibly would have, even after it acquires the 126 Multi-Role Combat Aircraft (MRCA) now on tender, with first deliveries due eight years hence.
    On the engine

    It is true that the Kaveri engine for the LCA that the Gas Turbine Research Establishment (GTRE) of the DRDO has been developing for 12 years has not yet met its technical performance targets and requires redevelopment. So far the GE 404 engine from the U.S., which powers the F-16 fighter-bomber, has been used to power the LCA. The problems the GTRE has with the Kaveri are not unusual in a complex fighter aircraft engine project being undertaken for the first time. Moreover, the financial sanction of about Rs.320 crore given for engine development was possibly only to cover the Project Definition Phase and some high-risk technology development effort. We do not know of a first-of-type high-technology fighter aircraft engine being developed anywhere in less than a multi-billion dollar programme and a 20-year-plus development cycle. Even Snecma, the sole fighter aircraft engine manufacturer in France, despite decades of experience in developing and manufacturing engines for Mirage III, V and F-1, took about a decade and $2.2 billion to develop the M-88 engine for the Mirage 2000. The development of the Kaveri is unlikely to cross $1 billion.

    The LCA with a GE 404 engine has done 800-plus hours of flight-testing. Even with that engine the performance has been not only vastly superior to that of even the recently upgraded MiG 21 BIS (the IAF is operating almost 400 of the series), but it has shown itself to be comparable in many critical parameters to the Mirage 2000. Modifications to the aircraft structure are under way to reduce weight and improve engine performance. When the GTRE’s joint venture with a leading foreign engine manufacturer for further development is completed in the next four years, the Kaveri will be brought up to a performance level, superior to the GE 404. Fitted with it, the LCA will be truly comparable to the Mirage 2000 and in many respects even superior. And all this in an aircraft much lighter than the Mirage 2000.

    As for network-centric capability, which intrinsically needs indigenous systems for secrecy, security and inter-operability, it is superior in the LCA compared to any aircraft in the IAF’s inventory.

    So it is a fallacy to think that we can continue the importing spree and still have such network-centric capability.

    As recently as in 2005, the IAF’s requirement for 126 new aircraft was only for an upgraded Mirage 2000. At Rs.120 crore to Rs.140 crore a plane, compared to at least double that amount for any of the aircraft types now bidding for the 126 MRCA, is not the LCA a highly cost-effective fighter for volume induction into the IAF?

    As for development costs, the LCA has remained well within the sanctioned $1.2 billion — which is about the lowest anywhere.Time overrun in the strict sense is only by a year or two, despite the sanctions. A first-of-type aircraft of this degree of complexity has not been developed anywhere in the West or in Russia in less than two to three decades.]

    The F16 series that was inducted into the U.S. Air Force in 1975 is today at Mark 60. That is how aircraft of this level of complexity are improved after induction. That this imperative applies even more to the LCA has to be recognised.

    It is for the Prime Minister and the Defence Minister to ensure that this effort is not belittled or scuttled, and that the LCA programme is given all-out support — as successive Prime Ministers have ensured for our atomic energy and space programmes.

    (Ashok Parthasarathi was Science Adviser to Prime Minister Indira Gandhi. Vice- Admiral (retired) Raman Puri was Chief of Integrated Defence Staff to the Chairman, Committee of Service Chiefs, remaining closely involved with the inter-service weapons acquisition process from October 2003 to February 2006).

    Reference :-

    http://www.hindu.com/2008/03/09/stories/2008030955051000.htm

    in reply to: ABM or ASAT #1788138
    Abhimanyu
    Participant

    It’s been a while since I was last briefed some on some of the programmes you mentioned, SM-3, but I’m sufficiently familiar with all of them to take a stab at answering your question.

    There are in fact three programmes – THAAD, Patriot PAC-3, and Standard Missile 3 (SM-3) – that we need to consider. The way that these evolved was partly constrained by the existing hardware that both services already possessed.

    Mr. Mercurius, thanks for your informative reply. I think to know the history of weapons development is important, so as to understand their use and how & what future weapons will be developed.

    Actually, I referred to Patriot and Thaad as a single system because both are complementary to each other in targeting in the exo and endo atmospheres respectively, exactly like India’s AAD-PAD combination. It is now clear that Patriot and Aegis have actually evolved independently from pre-existing rudimentary systems, whereas I thought they were begun separately to address the latest ballistic threats.

    in reply to: ABM or ASAT #1788311
    Abhimanyu
    Participant

    In my view, this interception by the US was an ASAT test in the “true sense” of the term, as there was target detection and tracking, which was not in any pre-determined orbit. The interceptor’s launch location and time was also dynamically decided.

    I would like to know the tactical or strategic reason if any, for developing 2 different kinds of ABM systems by the US i.e. the Thaad-Patriot system, and the Aegis system.
    Other than the fact that the Aegis uses a naval platform, and has a dedicated last-stage separation for calibrated maneuvering toward the target, there appears to be no significant difference between the development of these 2 systems.

Viewing 15 posts - 736 through 750 (of 832 total)